New Residential Construction in Thunder Bay: 95 Permits in Twelve Months

Newly built homes under construction on a residential street
Figures read October 9, 2026 from Builtie's permit data.

The City of Thunder Bay issued 95 permits for new houses, townhouses and apartment buildings from October 2025 to September 2026, 37 of them in the quarter to September. Builtie reads the permits, estimates each project's stage and attaches the builder or general contractor with a verified decision maker.

Find, qualify, identify, reach Findpermits, planning records,builder posts, site checks Qualifyscored 0 to 100 for yourprofile, stage and territory Identifythe company and the personwho awards the work ReachLinkedIn and email, underyour name, done for you

The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.

How many new residential construction permits Thunder Bay issued

MeasureThunder Bay
Permits issued, October 2025 to September 202695
July to September 202637
April to June 202628
Share of Thunder Bay's classified permits27%
Busiest monthOctober 2025 (14)
Rank among 23 markets19 of 23

This counts permits for new houses, townhouses and apartment buildings that Builtie classifies as new residential construction. The quarter to September was up 32% on the quarter before.

New Residential Construction in Thunder Bay, by month Oct 2025 14 Nov 2025 3 Dec 2025 4 Jan 2026 0 Feb 2026 3 Mar 2026 6 Apr 2026 9 May 2026 7 Jun 2026 12 Jul 2026 14 Aug 2026 14 Sep 2026 9

Permits issued per month, read October 9, 2026 from Builtie's permit data.

New Residential Construction: permits in twelve months, by market Austin 13,153 New York City 9,816 Miami-Dade 7,072 Calgary 6,083 Los Angeles 4,747 Nashville 3,351 Seattle 1,300 Vancouver 895 Fayetteville 872 Thunder Bay 95

The largest markets for new residential construction, read October 9, 2026.

Who decides on new residential construction in Thunder Bay

On new homes and apartment buildings the builder or developer awards the trades, through its purchasing manager or site superintendent; on custom homes the owner and designer have a say.

Trades these projects buy, and how many are open now

Each trade is bought at its own stage of the build. These are the trades new residential construction projects lean on, with the projects in Thunder Bay still inside each trade's award window today:

TradeProjects in its award window nowAward window
Framing600% to 20%
Concrete and Foundation34Before the start to 5%
Roofing7715% to 35%
Windows, Doors and Glazing8115% to 35%
Plumbing8620% to 45%
Electrical8720% to 45%
HVAC and Mechanical8720% to 45%
Drywall7635% to 60%
Cabinetry and Millwork5850% to 70%
Flooring6050% to 70%

What the Thunder Bay data covers

The data is Thunder Bay's own building permits. Neighbouring cities issue their own permits and are not in this count.

Other building types in Thunder Bay: residential renovation, commercial renovation.

Every trade: Thunder Bay construction leads by trade.

Plans

Builtie's Starter plan is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from CAD $1,500 a month on top of a Growth seat.

Frequently asked questions

How many new residential construction permits were issued in Thunder Bay in the last year?

95 from October 2025 to September 2026, 37 of them from July to September 2026, read October 9, 2026.

Who awards the trades on new residential construction projects?

On new homes and apartment buildings the builder or developer awards the trades, through its purchasing manager or site superintendent; on custom homes the owner and designer have a say.

How do I find new residential construction projects in Thunder Bay before they are awarded?

Work from the building permits: Builtie reads the City of Thunder Bay's permits, estimates each project's stage and shows the ones still inside your trade's award window, with the builder or general contractor and a verified decision maker.

What does Builtie cost?

Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.