Chicago Construction Permits, February 2026: 509 Issued

Wood-framed houses under construction in a new subdivision
Figures read October 9, 2026 from Builtie's permit data.

The City of Chicago issued 509 construction permits in February 2026. The largest group was residential renovation, with 128 permits.

Find, qualify, identify, reach Findpermits, planning records,builder posts, site checks Qualifyscored 0 to 100 for yourprofile, stage and territory Identifythe company and the personwho awards the work ReachLinkedIn and email, underyour name, done for you

The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.

Chicago construction permits in February 2026

MeasureFebruary 2026
Permits issued509
Previous month (January 2026)532
Same month last year (February 2025)484
Rank among 18 markets this month7 of 18

Against earlier months, February 2026 was down 4% on January 2026 (532) and up 5% on February 2025 (484).

Building type and workPermits
New Residential Construction31
Residential Renovation128
New Commercial Construction24
Commercial Renovation119
New Institutional Construction10
Institutional Renovation15
Industrial Renovation6
Chicago: permits issued per month Mar 2025 557 Apr 2025 725 May 2025 643 Jun 2025 699 Jul 2025 771 Aug 2025 682 Sep 2025 710 Oct 2025 718 Nov 2025 510 Dec 2025 519 Jan 2026 532 Feb 2026 509

The twelve months to February 2026, read October 9, 2026.

What it means for trades

A permit issued in February 2026 starts a clock. The early trades, site work, concrete, framing and structural steel, are bought in the next weeks; mechanical, electrical and plumbing a few months in; finishes and landscaping close to a year later on a typical build. Builtie tracks each project through those stages and shows it to a trade while its package is still open.

What the Chicago data covers

Chicago issues one combined permit per project, so the name on it is usually the general contractor or developer, which is the company a trade wants to reach.

← January 2026 · March 2026 →

All months: Chicago construction permits by month. Building types: new residential construction, residential renovation, new commercial construction, commercial renovation, new institutional construction, institutional renovation, industrial renovation.

Plans

Builtie's Starter plan is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from CAD $1,500 a month on top of a Growth seat.

Frequently asked questions

How many building permits were issued in Chicago in February 2026?

509, read October 9, 2026 from Builtie's permit data.

Is Chicago construction up or down?

February 2026 was down 4% on January 2026 (532) and up 5% on February 2025 (484).

Which trades should be calling builders about February 2026 permits?

Early trades first: site work, concrete, framing, structural steel and site security. Mechanical, electrical and plumbing follow a few months in, and finishes later still.