35 Shoreham Dr, Toronto: Apartment Building Renovation

Apartment Building Renovation at 35 Shoreham Dr, Toronto was permitted on March 10, 2025 with a stated construction value of under $1M. Replacement of domestic hot water boilers. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 35 Shoreham Dr, Toronto |
| Neighbourhood | Black Creek |
| Project | Apartment Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | March 10, 2025 |
| Stated construction value | under $1M |
| Estimated stage | Mechanical |
| Company named on the permit | Toronto Seniors Housing Corporation |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Replacement of domestic hot water boilers”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- Since July 20121 other permit at this address
- July 27, 2012Addition or alteration
- April 25, 2014Mechanical: roofing
- April 25, 2014Addition or alteration: roofing
- July 4, 2014Fire and life safety: fire protection · under $1M
- May 19, 2021Fire and life safety · under $1M
- March 10, 2025Mechanical: Apartment Building Renovation · under $1M (this page)
- April 2025Estimated construction start (estimate)
- October 2025Estimated completion (estimate; it may already be finished)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 4001 Steeles Ave WAddition or alteration: roofing · $1M to $5M · June 2026
- 170 Campus WalkAddition or alteration: plumbing · $1M to $5M · April 2026
2 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Toronto Seniors Housing Corporation has 12 other projects in Builtie
- Toronto · Addition or alteration: facade work · $1M to $5M · 2025
- Toronto · Mechanical: addition · under $1M · 2025
- Toronto · Addition or alteration: electrical · under $1M · 2025
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Apr 2025 – Oct 2025 | Estimate |
| Construction Site Security | Mar 2025 – May 2025 | Window passed (est.) |
| Painting | Apr 2025 – Jun 2025 | Window passed (est.) |
| Electrical | May 2025 – Jun 2025 | Window passed (est.) |
| HVAC and Mechanical | May 2025 – Jun 2025 | Window passed (est.) |
| Plumbing | Apr 2025 – Jun 2025 | Window passed (est.) |
| Fire Protection | May 2025 – Jun 2025 | Window passed (est.) |
| Signage and Wayfinding | Jun 2025 – Aug 2025 | Window passed (est.) |
| Insulation | May 2025 – Jun 2025 | Window passed (est.) |
| Drywall | May 2025 – Jul 2025 | Window passed (est.) |
| Low Voltage and Data | May 2025 – Jul 2025 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (April 2025) to the estimated completion (October 2025) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 4363 Jane St: Apartment Building Renovation
- 1-82 Flax Gardenway: Utility Facility Renovation
- 17 Woodcroft Cres: Apartment Building
- 25 King High Ave: Residential Project
- 24 Lowesmoor Ave: Retail Building
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 35 Shoreham Dr?
Apartment Building Renovation. Replacement of domestic hot water boilers
When was the permit issued for 35 Shoreham Dr?
March 10, 2025, by the City of Toronto.
Who is building 35 Shoreham Dr?
Toronto Seniors Housing Corporation is named on the permit. The decision makers and their contacts are in Builtie.
Which trades does 35 Shoreham Dr need now?
Estimated from the permit date, the award windows for site security, painting, electrical, HVAC, plumbing, fire protection, signage, insulation, drywall and low-voltage had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.