How Early Can You See a Construction Project? A Toronto Back-Test of 986 Permits
Start free trial 7 days, 10 projects: Toronto projects from the planning record to the permit, with the builder named where there is one.

Most large new buildings in Toronto are public long before the building permit. Builtie matched 986 New Building permits issued since 2015 to the City's development applications: 88% of buildings worth $10M or more (272 of 308) had a public planning application on file first (almost always a rezoning or site plan), and the site plan was filed a median of about 4 years (48.8 months) before the permit was issued. The numbers were read October 24, 2026 and cover the City of Toronto only.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The answer in one table
| Value stated on the permit | Permits | Public planning application first | Median, site plan to permit issued | Median, signal to permit issued | Median, signal to permit applied for |
|---|---|---|---|---|---|
| $10M+ | 308 | 272 (88%) | 48.8 months | 66.3 months | 33.2 months |
| $1M to $10M | 174 | 123 (71%) | 50.0 months | 61.8 months | 43.0 months |
| Under $1M or not stated | 504 | 376 (75%) | 50.3 months | 65.4 months | 37.3 months |
| All | 986 | 771 (78%) | 49.4 months | 65.3 months | 35.5 months |
"Signal" is the earlier of the most recent rezoning and the most recent site plan application filed before the permit application (any other application type when neither exists). Months are calendar months of 30.4 days. Read October 24, 2026.
How long before the permit the site plan was filed
308 New Building permits of $10M or more issued in Toronto since 2015, by years from the most recent site plan application to the permit's issue date. Read October 24, 2026.
For 186 of the 308 $10M+ buildings (60%) the site plan was filed three years or more before the permit was issued. 58 had no site plan on record at the same address, which includes projects whose address changed between planning and permit.
The lead is getting longer
| Permit issued in | Permits | Public first | Median, site plan to permit | Median, signal to permit |
|---|---|---|---|---|
| 2015 to 2018 | 269 | 74% | 40.9 months | 55.5 months |
| 2019 to 2022 | 281 | 78% | 46.9 months | 69.1 months |
| 2023 to 2026 | 436 | 81% | 54.9 months | 72.5 months |
The planning dataset starts in 2008, so a permit issued in 2015 can show at most seven years of history; the early figure is partly capped by that. The later years are not: projects permitted in 2023 to 2026 had been public a median of 72.5 months.
Four Toronto examples
| Address | Project | Rezoning filed | Site plan filed | Permit applied for | Permit issued |
|---|---|---|---|---|---|
| 8 Elm St | 69-storey mixed-use building, 819 units | July 2016 | September 2021 | October 2022 | March 2026 |
| 110 Broadway Ave | new building, $100M to $250M stated | August 2017 | October 2019 | October 2020 | February 2026 |
| 170 Roehampton Ave | 50-storey building, over $250M stated | June 2022 | June 2022 | October 2024 | July 2026 |
| 5207 Dundas St W | rental building of 725 units, over $250M stated | December 2019 | October 2022 | July 2023 | February 2026 |
Each date is the month the City records. No applicant, owner or planner is named here; the City's records name the planner, and the permit's applicant is not published by Builtie.
The signal ladder, measured
Construction data vendors often draw a ladder from land to permit with a lead time on each rung and no method behind it. This one shows what Builtie holds at each step and the lead it measured in Toronto, where it has the planning record. Elsewhere Builtie starts at the building permit.
| Step | What it is | In Builtie | Lead before the permit (Toronto) |
|---|---|---|---|
| Land changes hands | A sale or assembly of lots | No | Not measured |
| Rezoning or Official Plan Amendment | Permission to build something the zoning does not allow | Yes: Toronto, and Brampton, Markham, Mississauga, Oakville, Richmond Hill, Vaughan, York Region in Coming up | Part of the signal: median 66.3 months before the permit for $10M+ buildings |
| Site plan application | The building's layout, access and landscaping on the lot | Yes (same places) | Median 48.8 months before the permit for $10M+ buildings |
| Committee of Adjustment | Minor variances and severances, mostly houses and small buildings | Yes: Toronto | Not measured yet |
| Building permit applied for | Drawings submitted for code review | Yes: every covered market | A median 33.2 months after the signal |
| Building permit issued | Work can start | Yes: every covered market | The reference date |
| Inspections | The build passes each stage | Yes: Los Angeles; elsewhere the stage is Builtie's estimate | After the permit |
Method
- Permits. Every City of Toronto building permit with permit type "New Building" issued from January 1, 2015, read from the City's building permits open data (dataset). Revisions of one permit are grouped by permit number; the value is the highest stated on any revision.
- Planning applications. The City's development applications open data (dataset): rezonings and Official Plan Amendments, site plans, condominiums, subdivisions and part-lot control, 2008 onward, one row per application and address.
- Match. Same street name and street type, the permit's street number inside the application's number range, the application filed before the permit application and no more than 12 years before it.
- Signal date. The earlier of the most recent rezoning and the most recent site plan before the permit. Taking the earliest application at the address instead would overstate the lead: multi-phase sites carry applications for earlier phases.
- Excluded. Additions and alterations (interior fit-outs matched unrelated old rezonings) and Committee of Adjustment files (a different track, mostly houses).
Source and freshness. City of Toronto open data, read into Builtie daily; this page read October 24, 2026. Query rule and numbers are kept with the page's generator (docs/page-sources/andata.json) so the figure can be re-run.
Limits
- Toronto only. York Region's development applications are in Builtie (576 rows), but York's building permits are not, so there is nothing to test them against. No other market has a planning record in Builtie, and nothing here describes them.
- A floor, not a ceiling. A project whose address changed between planning and permit (land assemblies, renumbering) counts as having no signal.
- Street direction. The match ignores east and west; requiring it moves the $10M+ figure by one permit (271 of 308, 88.0%).
- Active permits. The City's permit dataset lists active permits; completed ones leave it, so the older years are a subset.
- No land title. Builtie does not hold ownership transfers, so the first rung of the ladder is not measured.
- Stated values. The band is the value declared on the permit, which is often low.
What this means if you sell to builders
Four years ahead is pipeline knowledge, not a bid. A trade cannot price a building whose design is still in site plan review. What it can do is learn the developer's name, watch the file and be known before the general contractor buys out the trades. On Builtie's current windows plumbing is typically chosen at 10% to 35% of the build and drywall at 25% to 45%, both after the permit.
In Builtie, GTA accounts see these applications in the Coming up tab, with a "Public since" date on Toronto projects, and can Watch a file to be emailed when it moves. Terms used here: site plan application, rezoning, Committee of Adjustment and award window.
Get new $1M+ projects in Toronto every week
Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
How to cite
Builtie, "How early can you see a construction project?", Toronto earliest-signal back-test, read October 24, 2026, builtie.com/how-early-can-you-see-a-construction-project/.
Plans and coverage
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Builtie's deepest coverage is in the Greater Toronto Area, where it started; depth in any city depends on what that municipality publishes. Ask for live sample projects in your own service area before you buy.
Frequently asked questions
How early is a Toronto construction project public?
For new buildings of $10M or more, 88% had a public rezoning or site plan application before the building permit, and the site plan was filed a median of 48.8 months (about 4 years) before the permit was issued. Builtie measured this on 986 permits, read October 24, 2026.
Does this apply outside Toronto?
Not as measured. Builtie holds planning applications for Toronto and several GTA municipalities, but only Toronto has both planning records and building permits in Builtie to test against. In other markets Builtie starts at the building permit.
Why use the site plan rather than the first application?
Large sites are often built in phases, and the earliest application at an address can belong to an earlier phase. The most recent site plan before the permit is the conservative figure.
Can I see these projects in Builtie?
Yes. GTA accounts see open planning applications in the Coming up tab, with a Public since date on Toronto projects, and can watch a file to be emailed when it moves.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.