Retail Building Renovation at 1061 The Queensway, Toronto was permitted on March 25, 2026 with a stated construction value of under $1M. Proposed installation of 250 kW rooftop load displacement solar PV system. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 1061 The Queensway, Toronto |
| Project | Retail Building Renovation |
| Building type | Commercial |
| Work | Renovation or alteration |
| Permit issued | March 25, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Sub-trades |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Proposed installation of 250 kW rooftop load displacement solar PV system”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- Since April 20077 other permits at this address
- April 11, 2007Plumbing · under $1M
- July 27, 2007Addition or alteration: demolition · under $1M
- March 11, 2014Drains and site services · $1M to $5M
- July 9, 2024Drains and site services · $1M to $5M
- December 17, 2024Mechanical
- March 25, 2026Addition or alteration: Retail Building Renovation · under $1M (this page)
- April 2026Estimated construction start (estimate)
- October 2026Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 1156 The QueenswayNew construction: excavation and shoring · $100M to $250M · December 2025
- 1053 The QueenswayNew construction: foundation · $5M to $10M · November 2025
- 1001 The QueenswayAddition or alteration: interior alteration · $1M to $5M · November 2025
- 45 Stanmills RdNew building · $1M to $5M · May 2026
- 40 Horner AveAddition or alteration: interior alteration · $1M to $5M · June 2026
8 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Apr 2026 – Oct 2026 | Estimate |
| Fire Protection | May 2026 – Jun 2026 | Window passed (est.) |
| Signage and Wayfinding | Jun 2026 – Aug 2026 | Window passed (est.) |
| Insulation | May 2026 – Jun 2026 | Window passed (est.) |
| Drywall | May 2026 – Jul 2026 | Window passed (est.) |
| Low Voltage and Data | May 2026 – Jul 2026 | Window passed (est.) |
| Tile | Jun 2026 – Jul 2026 | Window passed (est.) |
| Cabinetry and Millwork | May 2026 – Jul 2026 | Window passed (est.) |
| Flooring | Jun 2026 – Jul 2026 | Window passed (est.) |
| Countertops | Jun 2026 – Jul 2026 | Window passed (est.) |
| Finish Carpentry | Jun 2026 – Jul 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (April 2026) to the estimated completion (October 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 1967 Lawrence Ave E: Office and Tenant Fit-Out
- 150 Borough Dr: Office and Tenant Fit-Out
- 175 Plains Rd: School Renovation
- 60 Scottfield Dr: Long-Term Care Home Renovation
- 846 Eglinton Ave W: Commercial Project Renovation
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 1061 The Queensway?
Retail Building Renovation. Proposed installation of 250 kW rooftop load displacement solar PV system
When was the permit issued for 1061 The Queensway?
March 25, 2026, by the City of Toronto.
Who is building 1061 The Queensway?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 1061 The Queensway need now?
Estimated from the permit date, the award windows for fire protection, signage, insulation, drywall, low-voltage, tile, cabinetry, flooring, countertop and finish carpentry had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.