110 Mornelle Crt, Toronto: Apartment Building Renovation

Apartment Building Renovation at 110 Mornelle Crt, Toronto was permitted on September 16, 2025 with a stated construction value of under $1M. Garage repairs including localized concrete repairs, localized strengthening of garage roof and waterproofing of garage roof slab. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 110 Mornelle Crt, Toronto |
| Neighbourhood | Morningside |
| Project | Apartment Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | September 16, 2025 |
| Stated construction value | under $1M |
| Estimated stage | Sub-trades |
| Company named on the permit | Toronto Community Housing Corporation |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Garage repairs including localized concrete repairs, localized strengthening of garage roof and waterproofing of garage roof slab”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- July 4, 2006Addition or alteration · under $1M
- October 22, 2019Plumbing
- October 22, 2019Mechanical
- June 3, 2020Mechanical
- April 22, 2021Fire and life safety · under $1M
- September 16, 2025Addition or alteration: Apartment Building Renovation · under $1M (this page)
- October 2025Estimated construction start (estimate)
- April 2026Estimated completion (estimate; it may already be finished)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 1265 Military TrlMechanical · $1M to $5M · January 2026
- 685 Military TrlAddition or alteration: interior alteration · $1M to $5M · May 2026
2 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Toronto Community Housing Corporation has 84 other projects in Builtie
- Toronto · New building · $50M to $100M · 2025
- Toronto · Addition or alteration: structural work · $5M to $10M · 2026
- Toronto · Addition or alteration · $5M to $10M · 2024
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Oct 2025 – Apr 2026 | Estimate |
| Fire Protection | Nov 2025 – Dec 2025 | Window passed (est.) |
| Signage and Wayfinding | Dec 2025 – Feb 2026 | Window passed (est.) |
| Insulation | Nov 2025 – Dec 2025 | Window passed (est.) |
| Drywall | Dec 2025 – Jan 2026 | Window passed (est.) |
| Low Voltage and Data | Dec 2025 – Jan 2026 | Window passed (est.) |
| Tile | Dec 2025 – Jan 2026 | Window passed (est.) |
| Cabinetry and Millwork | Dec 2025 – Jan 2026 | Window passed (est.) |
| Flooring | Dec 2025 – Jan 2026 | Window passed (est.) |
| Countertops | Dec 2025 – Jan 2026 | Window passed (est.) |
| Finish Carpentry | Dec 2025 – Jan 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (October 2025) to the estimated completion (April 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 30 Livonia Pl: Apartment Building Renovation
- 42 Centre St: 3-Storey Retail Building
- 45 Amiens Rd: 2-Storey Retail Building
- 407 Arlington Ave: 3-Storey Retail Building
- 33 Gerrard St W: Hotel Renovation
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 110 Mornelle Crt?
Apartment Building Renovation. Garage repairs including localized concrete repairs, localized strengthening of garage roof and waterproofing of garage roof slab
When was the permit issued for 110 Mornelle Crt?
September 16, 2025, by the City of Toronto.
Who is building 110 Mornelle Crt?
Toronto Community Housing Corporation is named on the permit. The decision makers and their contacts are in Builtie.
Which trades does 110 Mornelle Crt need now?
Estimated from the permit date, the award windows for fire protection, signage, insulation, drywall, low-voltage, tile, cabinetry, flooring, countertop and finish carpentry had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.