2666 Olive Avenue, Altadena: Fire damage repair After the Eaton Fire

Fire damage repair at 2666 Olive Avenue, Altadena, after the January 2025 Eaton Fire, filed April 16, 2025. The plans show detached garage. It has cleared zoning review; full plans are next. Builtie follows every fire rebuild in Los Angeles, address by address.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The rebuild
| Address | 2666 Olive Avenue, Altadena, CA |
| Fire | Eaton Fire, January 2025 |
| Permits from | unincorporated Los Angeles County |
| Rebuild | Fire damage repair |
| What the plans show | detached garage |
| Like-for-like | No, the new home differs from the one lost |
| Where it stands | Zoning review cleared |
| Application filed | April 16, 2025 |
Read from the Los Angeles County's fire recovery records for 2666 Olive Avenue. Owners, applicants and case numbers are left out.
Rebuild progress
| County rebuild progress | |
|---|---|
| ✓ | Rebuild application received |
| ✓ | Zoning review cleared (now) |
| Full building plans received | |
| Building plans approved | |
| Building permit issued | |
| Rebuild in construction | |
| Construction completed |
The County tracks every fire rebuild through these seven steps. 2666 Olive Avenue is at step 2: zoning review cleared.
Other rebuilds on Olive Avenue
- 2629 Olive Avenue: Fire damage repair, completed
- 2636 Olive Avenue: Single-family home rebuild, plans approved
- 2637 Olive Avenue: Single-family home rebuild, plans in review
- 2648 Olive Avenue: Single-family home rebuild, permit issued
- 2656 Olive Avenue: Single-family home rebuild, under construction
- 2673 Olive Avenue: Accessory dwelling unit (ADU), completed
- 2683 Olive Avenue: Fire rebuild, plans in review
- 2695 Olive Avenue: Single-family home rebuild, under construction
All of them: fire rebuilds on Olive Avenue, Altadena. The whole area: the Altadena and Pasadena Eaton Fire rebuild tracker.
For contractors
Builtie follows the fire rebuilds across Los Angeles, from Pacific Palisades to Altadena, and shows a trade which rebuilds are at the point where its work is bought. Where a permit names the builder, Builtie attaches the decision makers and their verified contacts.
Plans
Builtie's Starter plan is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from CAD $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being rebuilt at 2666 Olive Avenue, Altadena?
Fire damage repair (detached garage), after the Eaton Fire of January 2025.
What is the status of the rebuild at 2666 Olive Avenue?
Zoning review cleared, read October 20, 2026.
Is 2666 Olive Avenue a like-for-like rebuild?
No, it is filed as a non-like-for-like rebuild.
What does Builtie cost?
Starter is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.