Single-Family House Renovation at 614 Beresford Ave, Toronto was permitted on March 23, 2026 with a stated construction value of under $1M. Renovation or addition to a single-family house. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 614 Beresford Ave, Toronto |
| Project | Single-Family House Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | March 23, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Sub-trades |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
Follow this project
We email you when it moves to a new status or build stage, plus the new $1M+ projects in Toronto once a week. Free, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- March 23, 2026Small Residential Projects: Single-Family House Renovation · under $1M (this page)
- March 23, 2026Plumbing
- March 23, 2026Mechanical
- April 2026Estimated construction start (estimate)
- October 2026Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 280 Quebec AveAddition or alteration: structural work · $1M to $5M · June 2026
- 30 Mould AveNew building · $1M to $5M · November 2025
- 2471 St Clair Ave WAddition or alteration: facade work · $1M to $5M · March 2026
- 462 Willard AveSmall Residential Projects: addition · $1M to $5M · May 2026
- 125 Evelyn CresAddition or alteration · $1M to $5M · June 2026
7 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Apr 2026 – Oct 2026 | Estimate |
| Fire Protection | May 2026 – Jun 2026 | Window passed (est.) |
| Signage and Wayfinding | Jun 2026 – Aug 2026 | Window passed (est.) |
| Insulation | May 2026 – Jun 2026 | Window passed (est.) |
| Drywall | May 2026 – Jul 2026 | Window passed (est.) |
| Low Voltage and Data | May 2026 – Jul 2026 | Window passed (est.) |
| Tile | Jun 2026 – Jul 2026 | Window passed (est.) |
| Cabinetry and Millwork | May 2026 – Jul 2026 | Window passed (est.) |
| Flooring | Jun 2026 – Jul 2026 | Window passed (est.) |
| Countertops | Jun 2026 – Jul 2026 | Window passed (est.) |
| Finish Carpentry | Jun 2026 – Jul 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (April 2026) to the estimated completion (October 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
Find work like this in Toronto
Leads for your trade: every trade in Toronto.
More projects: every Toronto project of $1M+ by address · major projects in Toronto.
Compare tools: The Best Construction Lead Generation Software in Ontario.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 15 Summerland Ter: Office and Tenant Fit-Out
- 8 Market St: Office and Tenant Fit-Out
- 44 King St W: Office and Tenant Fit-Out
- 85 Forty First St: School Renovation
- 2603 Bathurst St: Apartment Building Renovation
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 614 Beresford Ave?
Single-Family House Renovation. Renovation or addition to a single-family house.
When was the permit issued for 614 Beresford Ave?
March 23, 2026, by the City of Toronto.
Who is building 614 Beresford Ave?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 614 Beresford Ave need now?
Estimated from the permit date, the award windows for fire protection, signage, insulation, drywall, low-voltage, tile, cabinetry, flooring, countertop and finish carpentry had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.