Mixed-Use Building Renovation at 804 Danforth Ave, Toronto was permitted on May 19, 2026 with a stated construction value of under $1M. Repair and restoration of a fire-damaged existing mixed-use building, including architectural, structural, and mechanical work for a restaurant (ground floor and basement) and two residential dwelling units on the second floor. The street number for the… Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 804 Danforth Ave, Toronto |
| Neighbourhood | Danforth |
| Project | Mixed-Use Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | May 19, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Foundation |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Repair and restoration of a fire-damaged existing mixed-use building, including architectural, structural, and mechanical work for a restaurant (ground floor and basement) and two residential dwelling units on the second floor. The street number for the…”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- November 6, 2017Addition or alteration
- May 19, 2026Addition or alteration: Mixed-Use Building Renovation · under $1M (this page)
- May 21, 2026Mechanical: structural work
- June 2026Estimated construction start (estimate)
- December 2026Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby, including 3 more renovations within 1 km
- 400 Greenwood AveAddition or alteration: elevator · $1M to $5M · February 2026
- 690 Carlaw AveAddition or alteration · $1M to $5M · July 2026
- 1180 Danforth AveAddition or alteration: plumbing · $1M to $5M · June 2026
- 1117 Danforth AveMechanical · $1M to $5M · July 2026
9 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Jun 2026 – Dec 2026 | Estimate |
| Construction Site Security | May 2026 – Jul 2026 | Window passed (est.) |
| Concrete and Foundation | Jun 2026 | Window passed (est.) |
| Structural Steel | Jun 2026 – Jul 2026 | Window passed (est.) |
| Elevators | Jun 2026 – Jul 2026 | Window passed (est.) |
| Framing | Jun 2026 – Jul 2026 | Window passed (est.) |
| Painting | Jun 2026 – Aug 2026 | Window passed (est.) |
| Masonry | Jun 2026 – Jul 2026 | Window passed (est.) |
| Waterproofing | Jun 2026 – Jul 2026 | Window passed (est.) |
| Roofing | Jul 2026 – Aug 2026 | Window passed (est.) |
| Windows, Doors and Glazing | Jun 2026 – Aug 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (June 2026) to the estimated completion (December 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 200 Wolverleigh Blvd: Place of Worship Renovation
- 70 Woodington Ave: Office and Tenant Fit-Out
- 800 Greenwood Ave: School Renovation
- 53 Flerimac Rd: Retail Building
- 72 Bexhill Ave: Residential Project
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 804 Danforth Ave?
Mixed-Use Building Renovation. Repair and restoration of a fire-damaged existing mixed-use building, including architectural, structural, and mechanical work for a restaurant (ground floor and basement) and two residential dwelling units on the second floor. The street number for the…
When was the permit issued for 804 Danforth Ave?
May 19, 2026, by the City of Toronto.
Who is building 804 Danforth Ave?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 804 Danforth Ave need now?
Estimated from the permit date, the award windows for site security; concrete; structural steel; elevator; framing; painting; masonry; waterproofing; roofing; window, door and glazing had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.