1100 Lansdowne Ave, Toronto: Utility Facility Renovation

Utility Facility Renovation at 1100 Lansdowne Ave, Toronto was permitted on November 5, 2025 with a stated construction value of under $1M. Proposal to excavate to foundation wall to apply waterproofing for active leaks. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 1100 Lansdowne Ave, Toronto |
| Neighbourhood | Junction-Wallace Emerson |
| Project | Utility Facility Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | November 5, 2025 |
| Stated construction value | under $1M |
| Estimated stage | Framing |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Proposal to excavate to foundation wall to apply waterproofing for active leaks”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- Since February 20053 other permits at this address
- February 23, 2005Non-Residential Building Permit · $1M to $5M
- April 23, 2008Addition or alteration: interior alteration
- May 14, 2008Fire and life safety: fire protection · under $1M
- May 7, 2013Mechanical
- June 28, 2022Addition or alteration: interior alteration
- November 5, 2025Addition or alteration: Utility Facility Renovation · under $1M (this page)
- December 2025Estimated construction start (estimate)
- June 2026Estimated completion (estimate; it may already be finished)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 1245 Dupont StNew building · $100M to $250M · December 2025
- 980 Lansdowne AveNew construction · $25M to $50M · December 2025
- 1615 Dufferin StAddition or alteration · $10M to $25M · August 2026
- 95 Regal RdAddition or alteration · $1M to $5M · April 2026
- 1884 Davenport RdAddition or alteration: roofing · $1M to $5M · May 2026
14 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Dec 2025 – Jun 2026 | Estimate |
| Construction Site Security | Nov 2025 – Jan 2026 | Window passed (est.) |
| Painting | Dec 2025 – Feb 2026 | Window passed (est.) |
| Masonry | Dec 2025 – Jan 2026 | Window passed (est.) |
| Waterproofing | Dec 2025 – Jan 2026 | Window passed (est.) |
| Roofing | Dec 2025 – Jan 2026 | Window passed (est.) |
| Windows, Doors and Glazing | Dec 2025 – Jan 2026 | Window passed (est.) |
| Electrical | Jan 2026 – Feb 2026 | Window passed (est.) |
| HVAC and Mechanical | Jan 2026 – Feb 2026 | Window passed (est.) |
| Plumbing | Dec 2025 – Feb 2026 | Window passed (est.) |
| Fire Protection | Jan 2026 – Feb 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (December 2025) to the estimated completion (June 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 1540 Dupont St: Office and Tenant Fit-Out
- 259 Geary Ave: Office and Tenant Fit-Out
- 136 Millicent St: 3-Storey Apartment Building
- 1655 Dupont St: Office and Tenant Fit-Out
- 1 Ibms Ward 05: Transit Facility Renovation
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 1100 Lansdowne Ave?
Utility Facility Renovation. Proposal to excavate to foundation wall to apply waterproofing for active leaks
When was the permit issued for 1100 Lansdowne Ave?
November 5, 2025, by the City of Toronto.
Who is building 1100 Lansdowne Ave?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 1100 Lansdowne Ave need now?
Estimated from the permit date, the award windows for site security; painting; masonry; waterproofing; roofing; window, door and glazing; electrical; HVAC; plumbing; fire protection had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.