259 Geary Ave, Toronto: Office and Tenant Fit-Out

Office and Tenant Fit-Out at 259 Geary Ave, Toronto was permitted on July 18, 2025 with a stated construction value of under $1M. Proposal to demolish part of existing 2 storey building and construct new exterior infill walls, interior alterations for new electrical room. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 259 Geary Ave, Toronto |
| Neighbourhood | Junction-Wallace Emerson |
| Project | Office and Tenant Fit-Out |
| Building type | Commercial |
| Work | Renovation or alteration |
| Permit issued | July 18, 2025 |
| Stated construction value | under $1M |
| Estimated stage | Sub-trades |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Proposal to demolish part of existing 2 storey building and construct new exterior infill walls, interior alterations for new electrical room”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- July 18, 2025Addition or alteration: Office and Tenant Fit-Out · under $1M (this page)
- June 9, 2026Mechanical
- August 28, 2026New building
- September 1, 2026Drains and site services
- August 2025Estimated construction start (estimate)
- February 2026Estimated completion (estimate; it may already be finished)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 1245 Dupont StNew building · $100M to $250M · December 2025
- 640 Lansdowne AveNew construction · $100M to $250M · March 2026
- 980 Lansdowne AveNew construction · $25M to $50M · December 2025
- 1615 Dufferin StAddition or alteration · $10M to $25M · August 2026
- 95 Regal RdAddition or alteration · $1M to $5M · April 2026
17 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Aug 2025 – Feb 2026 | Estimate |
| Fire Protection | Sep 2025 – Oct 2025 | Window passed (est.) |
| Signage and Wayfinding | Oct 2025 – Dec 2025 | Window passed (est.) |
| Insulation | Sep 2025 – Oct 2025 | Window passed (est.) |
| Drywall | Oct 2025 – Nov 2025 | Window passed (est.) |
| Low Voltage and Data | Oct 2025 – Nov 2025 | Window passed (est.) |
| Tile | Oct 2025 – Nov 2025 | Window passed (est.) |
| Cabinetry and Millwork | Oct 2025 – Nov 2025 | Window passed (est.) |
| Flooring | Oct 2025 – Nov 2025 | Window passed (est.) |
| Countertops | Oct 2025 – Nov 2025 | Window passed (est.) |
| Finish Carpentry | Oct 2025 – Nov 2025 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (August 2025) to the estimated completion (February 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 1540 Dupont St: Office and Tenant Fit-Out
- 1100 Lansdowne Ave: Utility Facility Renovation
- 136 Millicent St: 3-Storey Apartment Building
- 1655 Dupont St: Office and Tenant Fit-Out
- 1 Ibms Ward 05: Transit Facility Renovation
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 259 Geary Ave?
Office and Tenant Fit-Out. Proposal to demolish part of existing 2 storey building and construct new exterior infill walls, interior alterations for new electrical room
When was the permit issued for 259 Geary Ave?
July 18, 2025, by the City of Toronto.
Who is building 259 Geary Ave?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 259 Geary Ave need now?
Estimated from the permit date, the award windows for fire protection, signage, insulation, drywall, low-voltage, tile, cabinetry, flooring, countertop and finish carpentry had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.