1639 Yonge St, Toronto: School Renovation

School Renovation at 1639 Yonge St, Toronto was permitted on December 9, 2025 with a stated construction value of under $1M. Proposal for interior alterations to office and library area, new universal washroom. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 1639 Yonge St, Toronto |
| Neighbourhood | Rosedale-Moore Park |
| Project | School Renovation |
| Building type | Institutional |
| Work | Renovation or alteration |
| Permit issued | December 9, 2025 |
| Stated construction value | under $1M |
| Estimated stage | Framing |
| Company named on the permit | Venture Construction Ltd. |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Proposal for interior alterations to office and library area, new universal washroom”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- Since October 20242 other permits at this address
- October 21, 2024Addition or alteration: excavation and shoring
- October 21, 2024Mechanical: excavation and shoring
- February 27, 2025Plumbing: excavation and shoring
- March 11, 2025Drains and site services · under $1M
- December 9, 2025Addition or alteration: School Renovation · under $1M (this page)
- May 4, 2026Fire and life safety: fire protection · under $1M
- January 2026Estimated construction start (estimate)
- July 2026Estimated completion (estimate; it may already be finished)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby, including 4 more renovations within 1 km
- 155 Balmoral AveNew building · $50M to $100M · June 2026
- 29 Pleasant BlvdAddition or alteration: excavation and shoring · $10M to $25M · September 2026
- 1951 Yonge StAddition or alteration: excavation and shoring · $1M to $5M · May 2026
- 111 Davisville AveAddition or alteration: mechanical · $1M to $5M · May 2026
- 1262 Yonge StAddition or alteration · $1M to $5M · May 2026
13 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Jan 2026 – Jul 2026 | Estimate |
| Construction Site Security | Dec 2025 – Feb 2026 | Window passed (est.) |
| Painting | Jan 2026 – Mar 2026 | Window passed (est.) |
| Masonry | Jan 2026 – Feb 2026 | Window passed (est.) |
| Waterproofing | Jan 2026 – Feb 2026 | Window passed (est.) |
| Roofing | Jan 2026 – Mar 2026 | Window passed (est.) |
| Windows, Doors and Glazing | Jan 2026 – Feb 2026 | Window passed (est.) |
| Electrical | Feb 2026 – Mar 2026 | Window passed (est.) |
| HVAC and Mechanical | Feb 2026 – Mar 2026 | Window passed (est.) |
| Plumbing | Jan 2026 – Mar 2026 | Window passed (est.) |
| Fire Protection | Feb 2026 – Mar 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (January 2026) to the estimated completion (July 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 50 Rosehill Ave: Apartment Building Renovation
- 40 Rosehill Ave: Condominium Renovation
- 21 Dale Ave: Apartment Building Renovation
- 21 Park Rd: Affordable Housing Renovation
- 160 Bloor St E: Office and Tenant Fit-Out
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 1639 Yonge St?
School Renovation. Proposal for interior alterations to office and library area, new universal washroom
When was the permit issued for 1639 Yonge St?
December 9, 2025, by the City of Toronto.
Who is building 1639 Yonge St?
Venture Construction Ltd. is named on the permit. The decision makers and their contacts are in Builtie.
Which trades does 1639 Yonge St need now?
Estimated from the permit date, the award windows for site security; painting; masonry; waterproofing; roofing; window, door and glazing; electrical; HVAC; plumbing; fire protection had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.