1780 Michael Lane, Pacific Palisades: New single-family home After the 2025 Fire

New single-family home at 1780 Michael Lane, Pacific Palisades, after the January 2025 Palisades Fire: the City of Los Angeles issued the building permit on June 25, 2026 with a stated construction value of $500K to $1M, and the rebuild is at the foundation stage (Builtie's estimate). Builtie tracks every Palisades rebuild permit, the stage of each build and the builder behind it.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The rebuild
| Address | 1780 Michael Lane, Pacific Palisades, Los Angeles, CA |
| City permit address | 1780 W Michael Lane |
| Rebuild | New single-family home |
| What the plans show | 2 storeys, attached garage, fire sprinklers throughout |
| Rebuild track | Like-for-like rebuild (the City's expedited track under Emergency Executive Order 1) |
| Building permit issued | June 25, 2026 |
| Status | At the foundation stage (Builtie's estimate) |
| Stated construction value | $500K to $1M |
| Builder named on the permits | Resolved in Builtie |
| Permits at this address since the fire | 2 |
The facts above are read from the City of Los Angeles building permits filed for 1780 Michael Lane since the January 2025 Palisades Fire. Owners and permit numbers are left out.
Permit timeline
| Issued | Permit | Status |
|---|---|---|
| June 25, 2026 | New single-family home | Issued |
| June 25, 2026 | Grading | Issued |
2 permits since June 25, 2026. A typical rebuild runs demolition and debris clearance, grading and retaining walls, the new building, then the pool and site work.
Where it stands
1780 Michael Lane is at the foundation stage (Builtie's estimate).
At that stage these trades are inside their award window, the stretch of the build when the builder decides who gets the work:
| Trade | Award window |
|---|---|
| Construction Site Security | Before the start to 15% |
| Concrete and Foundation | Before the start to 5% |
| Structural Steel | 0% to 15% |
| Elevators | 0% to 20% |
| Framing | 0% to 20% |
| Painting | 5% to 35% |
| Masonry | 10% to 30% |
| Waterproofing | 10% to 35% |
| Roofing | 15% to 35% |
| Windows, Doors and Glazing | 15% to 35% |
Other rebuilds on Michael Lane
- 1804 Michael Lane: New single-family home, foundation
- 1805 Michael Lane: New single-family home, framing
- 1805-1807 Michael Lane: Home addition, excavation
- 1811 Michael Lane: New single-family home, foundation
- 1822 Michael Lane: New single-family home, framing
- 1829 Michael Lane: New single-family home, framing
- 1834 Michael Lane: New single-family home, foundation
- 1836 Michael Lane: New single-family home, interior trades
All of them: fire rebuilds on Michael Lane. Every street: the Pacific Palisades fire rebuild tracker.
For contractors
Builtie tracks every Palisades rebuild permit as it is issued, estimates where each build stands, and names the builder behind it, so a trade can reach them while its part of the job is still open. The decision makers and their verified contacts are in Builtie.
Plans
Builtie's Starter plan is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from CAD $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 1780 Michael Lane, Pacific Palisades?
New single-family home (2 storeys, attached garage, fire sprinklers throughout), permitted June 25, 2026 after the January 2025 Palisades Fire.
What is the status of the rebuild at 1780 Michael Lane?
It is at the foundation stage (Builtie's estimate), read October 20, 2026.
Is 1780 Michael Lane a like-for-like rebuild?
Yes. The City marked its permit eligible for the expedited like-for-like track.
Who is building 1780 Michael Lane?
Builtie resolves the builder behind the permits and attaches a verified decision maker.
What does Builtie cost?
Starter is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.