Office and Tenant Fit-Out at 2196 Forest Avenue, Staten Island, New York City was permitted on August 14, 2026 with a stated construction value of under $1M. Proposed exterior renovation for Bank of America. No change to use, egress or occupancy. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 2196 Forest Avenue, Staten Island, New York City |
| Project | Office and Tenant Fit-Out |
| Building type | Commercial |
| Work | Renovation or alteration |
| Permit issued | August 14, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Foundation |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Proposed exterior renovation for Bank of America. No change to use, egress or occupancy”
Get new $1M+ projects in New York City every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- August 14, 2026Alteration: Office and Tenant Fit-Out · under $1M (this page)
- August 18, 2026Alteration · under $1M
- August 18, 2026Alteration · under $1M
- August 18, 2026Alteration · under $1M
- August 18, 2026Alteration · under $1M
- August 18, 2026Alteration · under $1M
- September 2026Estimated construction start (estimate)
- March 2027Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 80 Maple Parkway, Staten IslandAlteration: mechanical · $1M to $5M · March 2026
- 82 Davidson Street, Staten IslandAlteration CO: site protection · $1M to $5M · June 2026
2 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
The company behind this project has 5 other projects in Builtie
- ████████ ConstructionNew York City · Interior alteration · under $1M · 2026
- ████████ ConstructionNew York City · Interior alteration · under $1M · 2026
- ████████ ConstructionNew York · General Construction · 2026
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026: 9 to approach now, 1 passed.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Sep 2026 – Mar 2027 | Estimate |
| Construction Site Security | Aug 2026 – Oct 2026 | Approach now |
| Concrete and Foundation | Sep 2026 | Window passed (est.) |
| Structural Steel | Sep 2026 – Oct 2026 | Approach now |
| Elevators | Sep 2026 – Oct 2026 | Approach now |
| Framing | Sep 2026 – Oct 2026 | Approach now |
| Painting | Sep 2026 – Nov 2026 | Approach now |
| Masonry | Sep 2026 – Oct 2026 | Approach now |
| Waterproofing | Sep 2026 – Oct 2026 | Approach now |
| Roofing | Oct 2026 – Nov 2026 | Approach now |
| Windows, Doors and Glazing | Sep 2026 – Oct 2026 | Approach now |
How we estimate: each bar is the share of the build, from the estimated start (September 2026) to the estimated completion (March 2027) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in New York City
- 1774 62 Street, Brooklyn: Apartment Building Renovation
- 145 East 32 Street, Manhattan: Commercial Project Renovation
- 1234 College Avenue, Bronx: 3-Storey Office-to-Residential Conversion
- 353 West 57 Street, Manhattan: Apartment Building Renovation
- 57 East 55 Street, Manhattan: Commercial Project Renovation
All of them: construction projects in New York City by address. All five boroughs are in the feed, which has run since February 27, 2026. New York issues separate permits for each trade, so the firm named on a permit is often the trade contractor, an engineer or an expediter rather than the developer. Builtie groups the permits into projects and resolves the owner and builder separately.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 2196 Forest Avenue, Staten Island?
Office and Tenant Fit-Out. Proposed exterior renovation for Bank of America. No change to use, egress or occupancy
When was the permit issued for 2196 Forest Avenue, Staten Island?
August 14, 2026, by New York City.
Who is building 2196 Forest Avenue, Staten Island?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 2196 Forest Avenue, Staten Island need now?
Estimated as of October 2026, the trades to approach now are site security; structural steel; elevator; framing; painting; masonry; waterproofing; roofing; window, door and glazing. Already passed: concrete.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.