359 Roehampton Ave, Toronto: Apartment Building Renovation

Apartment Building Renovation at 359 Roehampton Ave, Toronto was permitted on December 5, 2025 with a stated construction value of under $1M. Proposal for alterations to roof system, attic space and soffits. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 359 Roehampton Ave, Toronto |
| Neighbourhood | Mount Pleasant East |
| Project | Apartment Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | December 5, 2025 |
| Stated construction value | under $1M |
| Estimated stage | Finishing |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Proposal for alterations to roof system, attic space and soffits”
Get new $1M+ projects in Toronto every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- February 4, 2010New building
- March 2, 2010Fire and life safety: fire protection
- December 5, 2025Addition or alteration: Apartment Building Renovation · under $1M (this page)
- December 2025Estimated construction start (estimate)
- July 2026Estimated completion (estimate; it may already be finished)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 170 Roehampton AveNew building · over $250M · July 2026
- 110 Broadway AveNew construction: excavation and shoring · $100M to $250M · February 2026
- 100 Broadway AveNew construction: excavation and shoring · $50M to $100M · February 2026
- 130 Eglinton Ave EMechanical · $1M to $5M · May 2026
- 389 Cleveland StMechanical · $1M to $5M · November 2025
10 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Dec 2025 – Jul 2026 | Estimate |
| Signage and Wayfinding | Mar 2026 – Apr 2026 | Window passed (est.) |
| Countertops | Feb 2026 – Mar 2026 | Window passed (est.) |
| Finish Carpentry | Feb 2026 – Mar 2026 | Window passed (est.) |
| Appliances and Equipment | Feb 2026 – Apr 2026 | Window passed (est.) |
| Landscaping | Mar 2026 – May 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (December 2025) to the estimated completion (July 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Toronto
- 801 Mount Pleasant Rd: Apartment Building Renovation
- 2551 Yonge St: Commercial Project Renovation
- 2525 Yonge St: Office and Tenant Fit-Out
- 299 Roehampton Ave: Apartment Building Renovation
- 134 Banff Rd: 2-Storey Retail Building
All of them: construction projects in Toronto by address. Builtie's Toronto data is the amalgamated City of Toronto, including Etobicoke, North York, Scarborough, East York and York. Mississauga, Brampton, Vaughan, Oakville and Burlington issue their own permits; Builtie has read them separately since October 2026, so a Toronto count is not a GTA count. Toronto states a construction cost on about a third of 2026 permits.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 359 Roehampton Ave?
Apartment Building Renovation. Proposal for alterations to roof system, attic space and soffits
When was the permit issued for 359 Roehampton Ave?
December 5, 2025, by the City of Toronto.
Who is building 359 Roehampton Ave?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 359 Roehampton Ave need now?
Estimated from the permit date, the award windows for signage; countertop; finish carpentry; appliance and equipment; landscaping had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.