3900 S Figueroa St, Los Angeles: 7-Storey Mixed-Use Building Renovation

7-Storey Mixed-Use Building Renovation at 3900 S Figueroa St, Los Angeles was permitted on July 13, 2026 with a stated construction value of under $1M. New roof mounted PV solar system on (e) 7 story mixed use apartment building. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 3900 S Figueroa St, Los Angeles |
| Project | 7-Storey Mixed-Use Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | July 13, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Framing |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “New roof mounted PV solar system on (e) 7 story mixed use apartment building”
Get new $1M+ projects in Los Angeles every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- Since February 20257 other permits at this address
- June 27, 2025Alteration · under $1M
- August 1, 2025Alteration: structural work · under $1M
- October 30, 2025Alteration · under $1M
- April 16, 2026Pool · under $1M
- April 16, 2026Pool · under $1M
- July 13, 2026Alteration: 7-Storey Mixed-Use Building Renovation · under $1M (this page)
- August 2026Estimated construction start (estimate)
- February 2027Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 800 W Martin Luther King Jr BlvdAddition · $5M to $10M · November 2025
- 941 W 37th PlAlteration: foundation · $5M to $10M · December 2025
- 3502 S Watt WayAlteration: mechanical · $1M to $5M · June 2026
- 4322 S Figueroa StInterior alteration · $1M to $5M · May 2026
4 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026: 6 to approach now, 4 passed.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Aug 2026 – Feb 2027 | Estimate |
| Construction Site Security | Jul 2026 – Sep 2026 | Window passed (est.) |
| Painting | Aug 2026 – Oct 2026 | Approach now |
| Masonry | Aug 2026 – Sep 2026 | Window passed (est.) |
| Waterproofing | Aug 2026 – Sep 2026 | Window passed (est.) |
| Roofing | Aug 2026 – Oct 2026 | Approach now |
| Windows, Doors and Glazing | Aug 2026 – Sep 2026 | Window passed (est.) |
| Electrical | Sep 2026 – Oct 2026 | Approach now |
| HVAC and Mechanical | Sep 2026 – Oct 2026 | Approach now |
| Plumbing | Aug 2026 – Oct 2026 | Approach now |
| Fire Protection | Sep 2026 – Oct 2026 | Approach now |
How we estimate: each bar is the share of the build, from the estimated start (August 2026) to the estimated completion (February 2027) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in Los Angeles
- 1130 N Seward St: Warehouse Renovation
- 5601 N De Soto Ave: Commercial Project Renovation
- 601 S Figueroa St: Office and Tenant Fit-Out
- 18700 W Ventura Blvd: Retail Building Renovation
- 2928 N North Main St: Office and Tenant Fit-Out
All of them: construction projects in Los Angeles by address. The data is the City of Los Angeles: the building permits the Department of Building and Safety (LADBS) issues. Santa Monica, Burbank, Long Beach and most other cities in Los Angeles County issue their own permits and are not in the feed today; Pasadena, Glendale and unincorporated Los Angeles County have been read separately since October 2026. The city's open dataset names no contractor, so Builtie reads each permit's LADBS record for the contractor and their CSLB license, the architect and the engineer. Many Los Angeles permits are owner-builder, and on those the architect is the first contact.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 3900 S Figueroa St?
7-Storey Mixed-Use Building Renovation. New roof mounted PV solar system on (e) 7 story mixed use apartment building
When was the permit issued for 3900 S Figueroa St?
July 13, 2026, by the City of Los Angeles.
Who is building 3900 S Figueroa St?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 3900 S Figueroa St need now?
Estimated as of October 2026, the trades to approach now are painting, roofing, electrical, HVAC, plumbing and fire protection. Already passed: site security; masonry; waterproofing; window, door and glazing.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.