43 Snyder Avenue, Brooklyn, New York City: Institutional Project Renovation
Follow this project · we email you when its status or build stage changes

Institutional Project Renovation at 43 Snyder Avenue, Brooklyn, New York City was permitted on August 27, 2026 with a stated construction value of $1M to $5M. Provide roof mounted guardrails. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 43 Snyder Avenue, Brooklyn, New York City |
| Project | Institutional Project Renovation |
| Building type | Institutional |
| Work | Renovation or alteration |
| Permit issued | August 27, 2026 |
| Stated construction value | $1M to $5M |
| Estimated stage | Foundation |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Provide roof mounted guardrails”
Follow this project
We email you when it moves to a new status or build stage, plus the new $1M+ projects in New York City once a week. Free, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- August 27, 2026Alteration: Institutional Project Renovation · $1M to $5M (this page)
- September 2026Estimated construction start (estimate)
- September 2027Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 13 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 155 Clarkson Avenue, BrooklynNew construction · $10M to $25M · March 2026
- 1027 Flatbush Avenue, BrooklynAlteration: demolition · $1M to $5M · October 2026
- 911 Flatbush Avenue, BrooklynAlteration: roofing · $1M to $5M · October 2026
- 902 Rogers Avenue, BrooklynAlteration CO: interior alteration · $1M to $5M · April 2026
4 projects of $1M+ were filed within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026: 9 to approach now, 1 coming up.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Sep 2026 – Sep 2027 | Estimate |
| Construction Site Security | Aug 2026 – Nov 2026 | Approach now |
| Concrete and Foundation | Sep 2026 – Oct 2026 | Approach now |
| Structural Steel | Sep 2026 – Nov 2026 | Approach now |
| Elevators | Sep 2026 – Dec 2026 | Approach now |
| Framing | Sep 2026 – Dec 2026 | Approach now |
| Painting | Oct 2026 – Feb 2027 | Approach now |
| Masonry | Sep 2026 – Nov 2026 | Approach now |
| Waterproofing | Sep 2026 – Nov 2026 | Approach now |
| Roofing | Nov 2026 – Jan 2027 | Coming up |
| Windows, Doors and Glazing | Oct 2026 – Dec 2026 | Approach now |
How we estimate: each bar is the share of the build, from the estimated start (September 2026) to the estimated completion (September 2027) above, when the builder usually picks that trade. It is not the builder's schedule.
Find work like this in New York City
Leads for your trade: Construction Site Security leads in New York City · Concrete and Foundation leads in New York City · Structural Steel leads in New York City · Elevators leads in New York City · every trade in New York City.
More projects: every New York City project of $1M+ by address · major projects in New York City.
Compare tools: The Best Construction Lead Generation Software in New York.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in New York City
- 1 Wall Street, Manhattan: Apartment Building Renovation
- 131 West 86 Street, Manhattan: Place of Worship Renovation
- 780 Post Avenue, Staten Island: School Renovation
- 107 Bank Street, Manhattan: Single-Family House Renovation
- 32 Richardson Street, Brooklyn: Single-Family House Renovation
All of them: construction projects in New York City by address. All five boroughs are in the feed, which has run since February 27, 2026. New York issues separate permits for each trade, so the firm named on a permit is often the trade contractor, an engineer or an expediter rather than the developer. Builtie groups the permits into projects and resolves the owner and builder separately.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 43 Snyder Avenue, Brooklyn?
Institutional Project Renovation. Provide roof mounted guardrails
When was the permit issued for 43 Snyder Avenue, Brooklyn?
August 27, 2026, by New York City.
Who is building 43 Snyder Avenue, Brooklyn?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 43 Snyder Avenue, Brooklyn need now?
Estimated as of October 2026, the trades to approach now are site security; concrete; structural steel; elevator; framing; painting; masonry; waterproofing; window, door and glazing. Coming up: roofing from November 2026.