Apartment Building Renovation at 60 Broadway, Manhattan, New York City was permitted on August 19, 2026 with a stated construction value of under $1M. Apartment renovations on 42nd and 43rd floor. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 60 Broadway, Manhattan, New York City |
| Project | Apartment Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | August 19, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Foundation |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Apartment renovations on 42nd and 43rd floor”
Get new $1M+ projects in New York City every week
Plus updates on this project. Free, one email a week, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- August 19, 2026Alteration: Apartment Building Renovation · under $1M (this page)
- September 2, 2026Alteration: mechanical · under $1M
- September 2, 2026Alteration: fire protection · under $1M
- September 2026Estimated construction start (estimate)
- March 2027Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 111 Wall Street, ManhattanAlteration CO: conversion to residential · $100M to $250M · April 2026
- 110 Maiden Lane, ManhattanAlteration CO: conversion to residential · $50M to $100M · July 2026
- 100 William Street, ManhattanAlteration CO: conversion to residential · $50M to $100M · March 2026
- 97 Barclay Street, ManhattanAlteration · $50M to $100M · July 2026
- 30 Broad Street, ManhattanAlteration CO: conversion to residential · $50M to $100M · August 2026
70 projects of $1M+ were permitted within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026: 9 to approach now, 1 passed.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Sep 2026 – Mar 2027 | Estimate |
| Construction Site Security | Aug 2026 – Oct 2026 | Approach now |
| Concrete and Foundation | Sep 2026 | Window passed (est.) |
| Structural Steel | Sep 2026 – Oct 2026 | Approach now |
| Elevators | Sep 2026 – Oct 2026 | Approach now |
| Framing | Sep 2026 – Oct 2026 | Approach now |
| Painting | Sep 2026 – Nov 2026 | Approach now |
| Masonry | Sep 2026 – Oct 2026 | Approach now |
| Waterproofing | Sep 2026 – Oct 2026 | Approach now |
| Roofing | Oct 2026 – Nov 2026 | Approach now |
| Windows, Doors and Glazing | Sep 2026 – Nov 2026 | Approach now |
How we estimate: each bar is the share of the build, from the estimated start (September 2026) to the estimated completion (March 2027) above, when the builder usually picks that trade. It is not the builder's schedule.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in New York City
- 386 Park Avenue South, Manhattan: Office and Tenant Fit-Out
- 107-15 Jamaica Avenue, Queens: Office and Tenant Fit-Out
- 25 Navy Street, Brooklyn: Retail Building Renovation
- 481 De Kalb Avenue, Brooklyn: 8-Storey Apartment Building
- 222-01 56 Avenue, Queens: Utility Facility Renovation
All of them: construction projects in New York City by address. All five boroughs are in the feed, which has run since February 27, 2026. New York issues separate permits for each trade, so the firm named on a permit is often the trade contractor, an engineer or an expediter rather than the developer. Builtie groups the permits into projects and resolves the owner and builder separately.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 60 Broadway, Manhattan?
Apartment Building Renovation. Apartment renovations on 42nd and 43rd floor
When was the permit issued for 60 Broadway, Manhattan?
August 19, 2026, by New York City.
Who is building 60 Broadway, Manhattan?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 60 Broadway, Manhattan need now?
Estimated as of October 2026, the trades to approach now are site security; structural steel; elevator; framing; painting; masonry; waterproofing; roofing; window, door and glazing. Already passed: concrete.
What does Builtie cost?
Starter is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.