New single-family home at 705 Via Santa Ynez, Pacific Palisades, after the January 2025 Palisades Fire: the City of Los Angeles issued the building permit on June 22, 2026 with a stated construction value of $500K to $1M, and the rebuild is at the foundation stage (Builtie's estimate). Builtie tracks every Palisades rebuild permit, the stage of each build and the builder behind it.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The rebuild
| Address | 705 Via Santa Ynez, Pacific Palisades, Los Angeles, CA |
| City permit address | 705 N Via Santa Ynez |
| Rebuild | New single-family home |
| What the plans show | 1 storey, attached garage, fire sprinklers throughout |
| Building permit issued | June 22, 2026 |
| Status | At the foundation stage (Builtie's estimate) |
| Stated construction value | $500K to $1M |
| Builder named on the permits | Multi Level Contractors LLC |
| Permits at this address since the fire | 3 |
The facts above are read from the City of Los Angeles building permits filed for 705 Via Santa Ynez since the January 2025 Palisades Fire. Owners and permit numbers are left out.
Permit timeline
| Issued | Permit | Status |
|---|---|---|
| June 22, 2026 | New single-family home | Issued |
| August 7, 2026 | Retaining wall | Issued |
| August 19, 2026 | Grading | Issued |
3 permits since June 22, 2026. A typical rebuild runs demolition and debris clearance, grading and retaining walls, the new building, then the pool and site work.
Where it stands
705 Via Santa Ynez is at the foundation stage (Builtie's estimate).
At that stage these trades are inside their award window, the stretch of the build when the builder decides who gets the work:
| Trade | Award window |
|---|---|
| Construction Site Security | Before the start to 15% |
| Concrete and Foundation | Before the start to 5% |
| Structural Steel | 0% to 15% |
| Elevators | 0% to 20% |
| Framing | 0% to 20% |
| Painting | 5% to 35% |
| Masonry | 10% to 30% |
| Waterproofing | 10% to 35% |
| Roofing | 15% to 35% |
| Windows, Doors and Glazing | 15% to 35% |
Other rebuilds on Via Santa Ynez
- 574 Via Santa Ynez: New single-family home, framing
- 676 Via Santa Ynez: New building, interior trades
All of them: fire rebuilds on Via Santa Ynez. Every street: the Pacific Palisades fire rebuild tracker.
For contractors
Builtie tracks every Palisades rebuild permit as it is issued, estimates where each build stands, and names the builder behind it, so a trade can reach them while its part of the job is still open. The decision makers and their verified contacts are in Builtie.
Plans
Builtie's Starter plan is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from CAD $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 705 Via Santa Ynez, Pacific Palisades?
New single-family home (1 storey, attached garage, fire sprinklers throughout), permitted June 22, 2026 after the January 2025 Palisades Fire.
What is the status of the rebuild at 705 Via Santa Ynez?
It is at the foundation stage (Builtie's estimate), read October 20, 2026.
Who is building 705 Via Santa Ynez?
Multi Level Contractors LLC is named on the permits. The decision makers and contacts are in Builtie.
What does Builtie cost?
Starter is $79 per seat per month (CAD) for 20 projects; Growth is $99 for 50 projects and adds LinkedIn and email outreach. There is a 7-day free trial with 10 projects.