Office and Tenant Fit-Out at 100 Wall Street, Manhattan, New York City was permitted on April 6, 2026 with a stated construction value of under $1M. INTERIOR RENOVATION OF OFFICE FLOOR FOR NON-LOAD BEARING PARTITIONS AND RELATED FINISHES 20th FLOOR CONSTRUCTION/21st FLOOR (MARKETING). NO CHANGE TO USE, EGRESS OR OCCUPANCY. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 100 Wall Street, Manhattan, New York City |
| Project | Office and Tenant Fit-Out |
| Building type | Commercial |
| Work | Renovation or alteration |
| Permit issued | April 6, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Framing |
| Company named on the permit | Reveal the builder — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “INTERIOR RENOVATION OF OFFICE FLOOR FOR NON-LOAD BEARING PARTITIONS AND RELATED FINISHES 20th FLOOR CONSTRUCTION/21st FLOOR (MARKETING). NO CHANGE TO USE, EGRESS OR OCCUPANCY”
Follow this project
We email you when it moves to a new status or build stage, plus the new $1M+ projects in New York City once a week. Free, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- Since March 20264 other permits at this address
- March 25, 2026Alteration: fire protection · under $1M
- April 6, 2026Alteration: Office and Tenant Fit-Out · under $1M (this page)
- May 26, 2026Alteration: demolition · under $1M
- May 26, 2026Alteration: demolition · $1M to $5M
- June 18, 2026Alteration: site protection · under $1M
- September 16, 2026Alteration: site protection · under $1M
- April 2026Estimated construction start (estimate)
- November 2026Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby
- 111 Wall Street, ManhattanAlteration CO: conversion to residential · $100M to $250M · April 2026
- 110 Maiden Lane, ManhattanAlteration CO: conversion to residential · $50M to $100M · July 2026
- 57 Broadway, ManhattanAlteration CO: conversion to residential · $50M to $100M · March 2026
- 100 William Street, ManhattanAlteration CO: conversion to residential · $50M to $100M · March 2026
- 30 Broad Street, ManhattanAlteration CO: conversion to residential · $50M to $100M · August 2026
61 projects of $1M+ were filed within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Apr 2026 – Nov 2026 | Estimate |
| Construction Site Security | Mar 2026 – May 2026 | Window passed (est.) |
| Painting | Apr 2026 – Jun 2026 | Window passed (est.) |
| Masonry | Apr 2026 – May 2026 | Window passed (est.) |
| Waterproofing | Apr 2026 – May 2026 | Window passed (est.) |
| Roofing | May 2026 – Jun 2026 | Window passed (est.) |
| Windows, Doors and Glazing | Apr 2026 – Jun 2026 | Window passed (est.) |
| Electrical | May 2026 – Jun 2026 | Window passed (est.) |
| HVAC and Mechanical | May 2026 – Jun 2026 | Window passed (est.) |
| Plumbing | May 2026 – Jun 2026 | Window passed (est.) |
| Fire Protection | May 2026 – Jun 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (April 2026) to the estimated completion (November 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
Find work like this in New York City
Leads for your trade: every trade in New York City.
More projects: every New York City project of $1M+ by address · major projects in New York City.
Compare tools: The Best Construction Lead Generation Software in New York.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in New York City
- 28-41 36 Street, Queens: Single-Family House Renovation
- 275 Seventh Avenue, Manhattan: Office and Tenant Fit-Out
- 2260 Grand Concourse, Bronx: Office and Tenant Fit-Out
- 10-10 44 Avenue, Queens: Industrial Building Renovation
- 112 Rear Waverly Place, Manhattan: Single-Family House Renovation
All of them: construction projects in New York City by address. All five boroughs are in the feed, which has run since February 27, 2026. New York issues separate permits for each trade, so the firm named on a permit is often the trade contractor, an engineer or an expediter rather than the developer. Builtie groups the permits into projects and resolves the owner and builder separately.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 100 Wall Street, Manhattan?
Office and Tenant Fit-Out. INTERIOR RENOVATION OF OFFICE FLOOR FOR NON-LOAD BEARING PARTITIONS AND RELATED FINISHES 20th FLOOR CONSTRUCTION/21st FLOOR (MARKETING). NO CHANGE TO USE, EGRESS OR OCCUPANCY
When was the permit issued for 100 Wall Street, Manhattan?
April 6, 2026, by New York City.
Who is building 100 Wall Street, Manhattan?
Builtie resolves the builder or general contractor behind the permit and attaches a verified decision maker.
Which trades does 100 Wall Street, Manhattan need now?
Estimated from the permit date, the award windows for site security; painting; masonry; waterproofing; roofing; window, door and glazing; electrical; HVAC; plumbing; fire protection had passed by October 2026; the project may already be finished. Builtie tracks the builder's next projects.