60 East 8 Street, Manhattan, New York City: Apartment Building Renovation
Follow this project · we email you when its status or build stage changes

Apartment Building Renovation at 60 East 8 Street, Manhattan, New York City was permitted on March 17, 2026 with a stated construction value of under $1M. Demo 1 bathroom, kitchen cabinets, walls at noted locations, new flooring, ceiling, new walls at noted locations. apt being changed from a 2 to 3 bedroom. no change in use, occupancy or means of egress. Builtie tracks the project's stage, the trades still being bought and the people who decide.
The same four steps, whether the buyer is a builder, a designer, an owner or a company you want to acquire.
The project
| Address | 60 East 8 Street, Manhattan, New York City |
| Project | Apartment Building Renovation |
| Building type | Residential |
| Work | Renovation or alteration |
| Permit issued | March 17, 2026 |
| Stated construction value | under $1M |
| Estimated stage | Sub-trades |
| Company named on the permit | Bednarz Building Corp See the decision makers — free trial |
| Decision makers and contacts | See who to contact — free trial |
From the permit: “Demo 1 bathroom, kitchen cabinets, walls at noted locations, new flooring, ceiling, new walls at noted locations. apt being changed from a 2 to 3 bedroom. no change in use, occupancy or means of egress”
Follow this project
We email you when it moves to a new status or build stage, plus the new $1M+ projects in New York City once a week. Free, unsubscribe anytime.
We email you once to confirm. Privacy
Where this project is
- March 17, 2026Alteration: Apartment Building Renovation · under $1M (this page)
- March 23, 2026Interior alteration · under $1M
- March 25, 2026Interior alteration · under $1M
- September 15, 2026Interior alteration · under $1M
- October 22, 2026Alteration
- October 22, 2026Interior alteration · under $1M
- March 2026Estimated construction start (estimate)
- October 2026Estimated completion (estimate)
How we estimate: from the permit date and its stated value, with the build lengths Builtie's project feed uses (about 7 months for a job this size). It is not the builder's schedule.
Other big projects nearby, including 3 more renovations within 1 km
- 301 East 17 Street, ManhattanAlteration: mechanical · $100M to $250M · June 2026
- 189 Allen Street, ManhattanInterior alteration · $10M to $25M · March 2026
- 122 5 Avenue, ManhattanInterior alteration · $10M to $25M · April 2026
- 25 East 11 Street, ManhattanAlteration CO · $10M to $25M · April 2026
- 580 Broadway, ManhattanAlteration CO: interior alteration · $10M to $25M · March 2026
88 projects of $1M+ were filed within 1 km in the last 12 months. See them all in Builtie →
Which trades are being bought now
When each trade on this project is usually picked, in calendar months (estimate). As of October 2026 every window below has passed (est.): the project may already be finished.
| Trade | When to approach (est.) | Status |
|---|---|---|
| Construction (est.) | Mar 2026 – Oct 2026 | Estimate |
| Fire Protection | Apr 2026 – Jun 2026 | Window passed (est.) |
| Signage and Wayfinding | Jun 2026 – Aug 2026 | Window passed (est.) |
| Insulation | May 2026 – Jun 2026 | Window passed (est.) |
| Drywall | May 2026 – Jun 2026 | Window passed (est.) |
| Low Voltage and Data | May 2026 – Jun 2026 | Window passed (est.) |
| Tile | May 2026 – Jul 2026 | Window passed (est.) |
| Cabinetry and Millwork | May 2026 – Jun 2026 | Window passed (est.) |
| Flooring | May 2026 – Jul 2026 | Window passed (est.) |
| Countertops | May 2026 – Jul 2026 | Window passed (est.) |
| Finish Carpentry | May 2026 – Jul 2026 | Window passed (est.) |
How we estimate: each bar is the share of the build, from the estimated start (March 2026) to the estimated completion (October 2026) above, when the builder usually picks that trade. It is not the builder's schedule.
Find work like this in New York City
Leads for your trade: every trade in New York City.
More projects: every New York City project of $1M+ by address · major projects in New York City.
Compare tools: The Best Construction Lead Generation Software in New York.
What Builtie adds
In Builtie: the decision makers on this project and their verified contacts, the trades already credited on it, the builder's other active permits, and LinkedIn and email outreach that runs while you work.
Other major projects in New York City
- 2816 Batchelder Street, Brooklyn: Single-Family House Renovation
- 161 Division Avenue, Brooklyn: Single-Family House Renovation
- 323 Carroll Street, Brooklyn: Single-Family House Renovation
- 1531 East 37 Street, Brooklyn: Single-Family House Renovation
- 209 East 17 Street, Manhattan: Duplex Renovation
All of them: construction projects in New York City by address. All five boroughs are in the feed, which has run since February 27, 2026. New York issues separate permits for each trade, so the firm named on a permit is often the trade contractor, an engineer or an expediter rather than the developer. Builtie groups the permits into projects and resolves the owner and builder separately.
Plans
Builtie's Starter plan is $79 per seat per month for 20 projects; Growth is $99 for 50 projects and adds the LinkedIn and email outreach you run yourself. Opening a project spends one credit, and the decision makers, emails, phones and AI call script inside it are included. Your monthly credits reset at each renewal, and extra credit packs are valid for 30 days. The free trial runs 7 days with 10 projects. Custom, where Builtie's team runs the outreach for you, starts from $1,500 a month on top of a Growth seat.
Frequently asked questions
What is being built at 60 East 8 Street, Manhattan?
Apartment Building Renovation. Demo 1 bathroom, kitchen cabinets, walls at noted locations, new flooring, ceiling, new walls at noted locations. apt being changed from a 2 to 3 bedroom. no change in use, occupancy or means of egress
When was the permit issued for 60 East 8 Street, Manhattan?
March 17, 2026, by New York City.
Who is building 60 East 8 Street, Manhattan?
Bednarz Building Corp is named on the permit. The decision makers and their contacts are in Builtie.
Which trades does 60 East 8 Street, Manhattan need now?